When is a Summary Task on the Critical Path?

Short answer: Never.

Long answer: Summary tasks are a collection of one or more child tasks. By definition, a summary task doesn’t represent any real work, resources, or deliverables, so summary tasks are neither on nor off the critical path of a project. Children of summary tasks can be on the critical path, assuming those children are not summary tasks themselves.