In this Primavera P6 project, every activity has a value for Budgeted Total Cost and is also assigned a Resource:
Each of those resources also belongs to a Department:
In the coming steps, we'll graph the cost, and then slice and dice it by resource and by department.
-
Decide which activities from Primavera P6 you want to include in your OnePager Gantt chart. The easiest way to do this is to set up a user-defined field, like this::

-
Export your Primavera P6 project to an XML format. You can also export to XER, but XML is better-suited to cost reporting. Once your export is complete, click the OnePager button on the desktop to start building your Gantt chart with cost:

-
On OnePager's start screen, click NEW to begin creating your Gantt chart. The import wizard will appear. Browse for your XML or XER file from Primavera P6. Choose the Monthly Cost for Primavera template as a starting point. If you've chosen to filter your activities by a user-defined field, apply that filter in the Task Selection section:

-
Click Create new chart OnePager will build your initial Gantt chart, showing selected activities at the bottom and a monthly line graph of Actual Total Cost at the top:

In the next section, we'll customize the graph.
Free Trial
Creating a Bar Graph of Project Budget by Department
In the next few steps, we'll show you how to create a column (bar) graph that looks at the Budgeted Total Cost field from Primavera P6 on a quarterly basis.
-
Currently, our Gantt chart has a line graph that looks at the monthly values of the Actual Total Cost field. We want to change that to a column graph that looks at the quarterly values of the Budgeted Total Cost field instead. To do this, go to Home > Chart Properties > Graphs/Data Cells. Change the settings for your graph as follows:
- Time Unit: Quarter
- Field: Budgeted Total Cost
- Graph Type: Column

-
Click OK, and OnePager will update your graph to show the quarterly project budget, like this:

Free Trial
Slicing and Dicing Cost by Resource
OnePager can also slice and dice your column graph so that you can see how much of the quarterly project cost is allocated to each resource.
-
Return to Home > Chart Properties > Graphs/Data Cells and click on the Pivot Series button:

-
Check the box to Pivot vertically, and select the Resource field from Primavera P6. OnePager will assign a different color to each resource in your schedule:

-
Click OK. Enable the Legend and then click OK a second time:

-
OnePager will update each quarterly column to a stacked column with segmented color for each resource.

In Q4 2025, the project budget is split by Amit Chopra and Robert Lincoln. In Q1 2026, Amit Chopra is responsible for the majority of the budget, with Robert Lincoln and Cindy Lee also contributing.
Free Trial
Slicing and Dicing Budget by Department
Instead of looking at budget by resource, you can also look at budget on a departmental level, or can look at resources and departments simultaneously.
-
Return to Home > Chart Properties > Graphs/Data Cells. Click the Pivot Series button again, but this time, navigate to the Horizontal Pivot tab. Choose the Department (Description) field, which is a global activity code from P6, assigning each resource to an overarching department:

-
Click OK and OnePager will update the graph again. It's still color-coded by resource, but notice that each department now has its own column, splayed left-to-right:

We can see that the Operations and IT departments represent all of the project budget until Q1 2027, when the Sales and Marketing department starts contributing to project cost.
Get started today by downloading a free trial.