To get started, download a free trial of OnePager and then follow these steps:
-
In this example Smartsheet project, we have four phases, each with multiple milestones. We'll import the milestones into the timeline, so that all milestones from a certain parent row end up on the same timeline:
-
To select only the the key milestones in Smartsheet, we can use a checkbox field. Right-click on any existing Smartsheet column, and choose Insert Column Left. Name the checkbox field OnePager:
-
Now, use the OnePager column to check all of the key milestones that you want to include in your timeline. Save your Smartsheet project once you are finished selecting milestones:
-
Launch OnePager using the desktop icon:
-
On the OnePager start screen, click New:
-
On the import wizard, choose Select > BROWSE Smartsheet:
If this is your first time connecting OnePager to Smartsheet, Smartsheet will ask you for your username and password, and whether you want to allow OnePager to have read-only access to your Smartsheet project for the purposes of building your timeline.
-
Select your Smartsheet project and click OK:
-
OnePager has a template that is specifically designed for milestone timelines from Smartsheet. To use it, go to Change > BROWSE FILES and select the Birds on a Wire Chart for Smartsheet template that comes with the trial license.
-
Give your timeline a name, and select the OnePager checkbox field as your filter. Then, click Next, followed by Create New Chart:
-
OnePager will import your selected milestones from Smartsheet, and will align all milestones that share the same parent row into a single row on your timeline:
-
If you'd like to add a splash of color to your timeline, you can tell OnePager to assign a different color to each phase of your project. To do this, go to Home > Chart Properties > Milestones and change the Foreground Color to look at the Level 1 Summary Name, which corresponds to the phase names that we have in our parent rows back in Smartsheet:
-
After you click OK, OnePager will reapply colors to your chart so that each phase from Smartsheet gets a unique color:
That's it! If you'd like to build a timeline of milestones from your own Smartsheet project, we invite you to download a free trial of OnePager today: