Adding a new Milestone to Smartsheet

How insert a new milestone into your Smartsheet project

  1. Open an existing Smartsheet project that has some tasks in it. It should look something like you see below.

    Smartsheet project with four tasks

  2. In this example, we will insert a milestone between “Task B” and “Task C”. To do this, you must first select “Task C” as you see below.

    Smartsheet project with four tasks

  3. Press the Insert key on your keyboard to insert a row:

    Smartsheet project with a blank row inserted for a new task.

  4. After pressing the insert key, you should see a blank row where you can enter the new milestone.

    Smartsheet project with a new task inserted

  5. Enter the milestone information and set the duration to “0 days.” After that, enter the start date. Smartsheet will automatically set the finish date and the start date equal. The reason for this is because the milestone is zero days in duration.

    Smartsheet project with a new task inserted